COURT
FACILITIES AND COUNTY
SPACE NEEDS COMMITTEE
SEPTEMBER 7, 2011
** NOT APPROVED **
Members Present:
D. Pullen, D. Fanton, G.
Benson, D. Cady, P. Curran, K. Graves, C. Crandall
Others Present: M. Alger, M. Armstrong (Bovis), M. Balling
(Bovis), D. Button, A. Finnemore, M. Healy, T. Hopkins, J. Margeson, T. Miner, B.
Riehle, D. Roeske, T. Ross, E. Ruckle, F. Sinclair, R. Starks; Media: J. Cole and D. Roorbach, Olean Times Herald
Call to Order:
3:00
p.m. by
Committee Chairman David Pullen
Approval of Minutes:
The minutes from
the meeting of August 3, 2011, were approved following a motion made by
Legislator Curran, seconded by Legislator Graves and carried.
COURT FACILITIES PROJECT,
CONSTRUCTION MANAGER UPDATE:
Mark Balling and Mark Armstrong from
Bovis Lend Lease presented a progress report (copy of report attached to
original minutes).
Budget Review – Anticipated
Cost Report:
Mark Balling noted that the
Anticipated Cost Report reflected work through August, and approximately 89
percent of the construction cost has been billed for. The balance in construction contingency is $155,304.60. It’s safe to say we will not come anywhere
close to using that. There are a couple
of recent changes under incidental costs.
Furniture and Equipment was increased by $3,000 from last month due to
the Judge’s credenza, but Javen will be paying for that through the damaged
furniture credit change order. There is
also a small adjustment under Telephone/Data Servers/Equipment for a couple of uninterrupted
power supply units the County purchased for the IT area.
Change Event Log (Changes
from Last Month):
Approved
Revisions:
·
#118 Sanitary Piping Revisions – around the existing building system – $3,781.04
·
#120 Firesafe Pre-Existing Floor Penetrations – less than estimated –
$4,434.62
Approximated
Revisions (Pending):
·
#125 Exhaust System Revisions – proposed price of $2,648.61, but waiting
for a reply from Javen as they actually owe on some things not installed
·
#144 Delete Top Course of Paving on Back Parking Lot – the County will
be doing this work to coordinate with the Maintenance Building
– estimated credit ($35,000)
·
#145 Relocate the Fan Coil Unit in Room 204 (Security Office) –
estimated $2,500
·
#146 In Existing Courthouse, Change all VCT-4 to VCT-1 – floor tile
changed from black to tan – estimated $3,000, but waiting for restocking price
for swap out
·
#147 Delete Law Library Window Infills and Install Opaque Film on Glass –
estimated credit ($1,500)
·
#148 Remove Existing Door and Frame at the Main Floor Level at Bottom of
Ornamental Staircase – at County’s request – estimated $600 – Legislator Graves
questioned if there was some building code reason that
the door was there, and stated that he didn’t want to take it out then have to
put it back. Public Works Superintendent
David Roeske noted that the doorway was not wide enough. Mr. Balling explained that the door doesn’t
meet code now, because it swings the wrong way, but he will check on it.
The project is currently $1.869 million
under budget, but Mr. Balling pointed out there is a
lot of unused contingency, so that number could easily end up at $2 million.
Site Overview – Safety
Report
Mark Armstrong reported that the
project has a clean safety record for this reporting period.
Work Performed in the Past Month
(August):
·
Phase II exterior and civil punch list nearly completed
·
Late Phase II change events completed
·
Ground floor vestibule underway
·
Final coat of paint nearly completed
·
Electrical lighting and finishes nearly completed on all floors; electrical
inspection taking place in most areas today, to be finished when the handicap
lift is done
·
HVAC control valves completed
·
Plumbing completed
·
Millwork completed
·
Carpeting and vinyl flooring nearly completed
·
Doors and hardware underway
Sixty-Day Look Ahead (September
and October):
- Painting completed
- Electrical work completed
- Doors and hardware installed
- Security system installed
- Flooring completed
- Handicap lift installed
- Punch list underway
- Late changes completed
- Closeout requirements in process
- NYS Certificate of Compliance issued
- County projects: DMV, Fire
Apparatus Access Drive, and Maintenance Building
ongoing
Mr. Balling noted that the state
inspection of the renovations is scheduled to take place in about two
weeks. Punch lists will begin tomorrow
on the completed rooms, the handicap lift will be completed on the 22nd,
furniture will be delivered on the 22nd, and hopefully the formal
blessing for moving back into the Courthouse will be given on the 23rd. There will still be some punch list items to
complete, and he’d like to see the list before he says the project is done, but
occupancy should be able to take place by the end of September. Chairman Crandall remarked that there were a
lot of details and millwork that seemed to drag on with the Addition, and asked
if there was less of that type of thing with the renovation phase so that this
part would go quicker. Mr. Balling
replied that because of how some of the issues went with the Addition Phase,
the renovations went more smoothly, and there were also different
circumstances. They are pushing them to
finish.
Within 30 days, the project will be totally complete,
unless there are some punch list items and late changes. Mr. Balling suggested that they continue to
come to committee meetings, depending on changes, to provide updates on the financial
status of the project.
MAINTENANCE BUILDING – REVIEW
OF COST ALLOCATION:
Committee Chairman David Pullen noted that there have
been questions on the cost of the Maintenance
Building. The original budget figure included on Bovis
Lend Lease’s anticipated cost report for the Court Facilities Project (page 3) was
$14.48 million. Currently, the project
is about $1.869 million under budget, but considering contingency balances, it
may end up $2 million under budget. Comments
have been made that we’re not counting everything. One significant item is the Maintenance Building. Right now, the cost of that building is included
in the Public Works budget, even though it was the Court Facilities Project
that created the need to replace the previous Maintenance Building
in a new location. The cost of the new Maintenance Building is $364,000, not including the
inside finish work. Public Works’ 2011
budget includes $380,000 for the building.
Mr. Pullen questioned if that cost is in reality a Court Facilities
Project cost, and if it should come out of what would otherwise appear to be our
surplus for that project. Is it accurate
and fair to the public and the various departments involved to not include that
cost? Public Works Superintendent David Roeske
felt the Maintenance
Building should have been
part of the planning process for the Court Facilities Project. Instead, his department has had to do the
planning and try to budget for it.
Public Works Committee Chairman Dwight Fanton agreed that the cost
should have been included in the Court Facilities Project funding, especially
since there was going to be a fund balance.
He stated that in addition to having to replace a building that they
lost, they now have a lot larger facility to maintain, so they’ll need a little
more room for storage and the maintenance operation.
Legislator Donald Cady noted that the $380,000 presently
in the Public Works budget would be freed up by transferring the expense of the
Maintenance Building to the Court Facilities Project
contingency funds, and he questioned what it would be used for. Mr. Fanton responded that there has been
discussion on possibly revamping the former Jail elevator to provide better
access to the upper floor (next item on the agenda). An estimate of $58,000 was received to put in
a new elevator car and new controls, but that estimate does not include a new
opening on the ground floor. Mr. Roeske
pointed out that there are other things to consider that were not budgeted,
such as the renovations asked for in Probation, the County Attorney’s
Office, Public Works, and some others.
Mr. Cady asked if everything could be totaled to allow transferring a
lump sum. Committee Chairman Pullen
pointed out that although these other issues are tied together, they’re not
really part of the bonding done for the Court Facilities Project. The bonding would cover the old Courthouse,
the Addition, the parking lot, and things related to it, but it’s limited and
does not include work in the County Office Building
or the Support Collection Building. That would have to be covered by other County
funding sources. For a project that was
forced on us and during planning we had no idea how the cost would come out, $12.6
million is a good outcome. Covering the
cost for the Maintenance Building under the Court Facilities Project funding
allows some flexibility in using the Public Works funds to include some things
not in the original plan, such as changes in the County Attorney’s
Office, Department of Motor Vehicles, and Probation.
A motion was made by Legislator Fanton, seconded by
Legislator Cady and carried to approve moving the expense of the Maintenance Building at $380,000 to be paid out of
the Court Facilities Project Capital Fund rather than the Public Works budget. This matter will be referred to Ways and
Means, and they will also determine how to utilize the funds freed up in the
Public Works budget, based on the recommendations of the Court Facilities and
County Space Needs Committee. County Administrator
John Margeson noted that this action, if approved, will allow utilizing
currently funded monies to do projects other than the Maintenance
Building, because the Maintenance Building will be covered by the Court Facilities
Capital Fund. Mr. Margeson will check
with bond counsel and the County Attorney to see if a resolution is necessary or if we
can simply pay for construction of the Maintenance Building
out of the capital fund already established for the Court Facilities
Project. He already spoke with bond
counsel about utilizing those surplus funds from the bond to pay for the Maintenance Building, and he’s been assured that
it’s legitimate to do that. Mr. Margeson
will attend the Ways and Means meeting to report on whether a resolution is
necessary. Referred to Ways and Means
Legislator Graves noted
that there are a lot of issues and areas that need to be addressed, and he’d
like to see something done about the cramped conditions in Social Services. Mr. Graves suggested some planning sessions
to establish a written action agenda, including goals and anticipated
completion dates. Legislator Fanton
pointed out that this action referred to Ways and Means will allow some of these
other issues to be addressed because we’ll have the funding for it.
JAIL ELEVATOR – DISCUSSION OF POSSIBLE ALTERNATE USAGE:
Committee Chairman David Pullen
reported that there has been discussion related to the former Jail elevator. Currently the only access is in the former Sheriff Control Center
(the “Bubble”) on the ground floor, in the former Jail on the third floor, and limited
use in the “Tank” in the breezeway area on the second floor, formerly used for
taking prisoners from the Jail to the main court room. The public has never had access to that
elevator. The Sheriff still needs to
control that area for security purposes.
If left the way it is, that elevator remains unavailable to anyone other
than Sheriff’s personnel for access to the top floor. That has stymied the ability to do any planning. Public Works Superintendent David Roeske
contacted Otis Elevator for estimates on a new car that would open on the
ground floor and possibly on the first floor.
We already have an opening on the second and third floors. It would include the new car and all the
controls that the public would need to use.
We’d have to put in a new entrance in the breezeway. The shaft, all the power equipment, and the piston
would remain.
An estimate of $58,000 was
received for the new elevator car and controls, but that estimate does not
include the new openings.
When asked about the
Sheriff security issue, Mr. Pullen explained that the
Sheriff will not allow us to have the general public in the Bubble area, but if
the public would only be able to access the elevator from this side, rather
than the Bubble side, with a lockout function, the Sheriff would approve of
that. The new elevator car would have
double doors. The Sheriff doesn’t use
the top floor, which is presently just used for storage. The stairs go all the way up, but given the ADA and other
requirements, we’ve been unable to consider using that
16,000 square feet of space for anything involving the general public or the
general County employee population because of the lack of handicap access. Access points on each floor were discussed.
A motion was made by Legislator
Graves, seconded by Legislator Curran and carried to authorize exploring the possibility
of converting the former Jail elevator for use by the general public and County
employees in a manner acceptable to the Sheriff to provide access to the top
floor of the County Office Building, and obtaining an estimate from Public
Works for the cost of cutting through and rebuilding new openings. Referred to Ways and Means
Legislator Healy questioned
alternate ways of providing access to the elevator on the ground floor while
still avoiding the Bubble, and he pointed out that at some point, we might want
to consider making that entrance a security station or leaving room for that
option. It should also be visible to the
Sheriff’s security “Bubble,” so space should be left to allow for that. At the same time, we also need to consider
plans for where the second Assistant Public Defender will be located or if the
Public Defender’s Office should be relocated.
Legislator Graves reiterated the need
to plan ahead and noted that the top floor is very secure, even if it is
remote. Committee Chairman Pullen noted
that during election times, the Board of Elections needs priority use of the
former Jail elevator for moving the voting machines from the third floor
storage. There has been discussion of
moving the voting machines to the new storage building being constructed near
the Landfill, so that won’t be a long-term obstacle. Until then, we would have to coordinate to
prevent interference with the Board of Elections. Public Works Superintendent David Roeske
noted that the new storage building should be completed within a couple of
months.
Committee Chairman David Pullen
commented that in the past, there has been discussion on offering the
opportunity to one of the County’s educational facilities to develop a plan for
the third floor of the County
Office Building. Skilled staff with training in design and
building trades would provide the supervision and students would design and construct
some of what we need. This would serve
several functions: it would relieve
Public Works from having to do the build-out, provides the opportunity for
cooperation and collaboration, and allows the students to develop building
skills beyond what they would normally be working on. The concept hasn’t been explored in detail,
but if Ways and Means concurs, maybe we can proceed with looking into it. The Committee has had to deal with the hottest
issues as we went along, but maybe now we can start planning ahead and planning
to succeed.
PARKING PLAN REVIEW:
Committee Chairman Pullen reported
that Public Works Superintendent David Roeske has indicated that until the Maintenance Building is further along, he won’t know
exactly how many parking spots will be available in the back parking lot and
around the Courthouse Addition. Without
that information, the planning process would be very challenging. The parking plan can be discussed further at
the October meeting, when Mr. Roeske should be closer to having those
numbers. Mr. Roeske stated that he hopes
to pave and mark the back lot during the first two weeks in October.
Mr. Pullen spoke briefly about his
idea for a three-level parking garage with dedicated parking spots for those
willing to pay rentals (also mentioned at the August 3 meeting). Mr. Roeske said he could talk with some
contractors to explore its feasibility and potential cost. We may then want to survey employees for
potential interest, and there would be other factors to consider. Legislator Healy noted that there have been
comments from the public about building a parking lot on the Court Street properties
that the County purchased, and he questioned how many parking spots that would
create. Mr. Pullen noted that there are
probably several answers to that depending on whether one or both buildings
were demolished and if all the space was used for parking. It was noted that the small lot below the
back corner of the back parking lot has not been acquired yet and will need
full Board approval. Mr. Pullen will be
working with Deputy County Administrator Mitch Alger on a parking proposal for
the October meeting.
Next Meeting:
Wednesday, October 5, 2011, at 3 p.m.
Adjournment:
The meeting was adjourned at 4:10 p.m. following a motion made by Legislator
Graves, seconded by Legislator Cady and carried.