COURT
FACILITIES AND
SPECIAL MEETING – JUNE 29, 2011
** NOT APPROVED **
Members Present: D. Pullen, D. Fanton, G.
Benson, D. Cady, K. Graves, C. Crandall
Absent: P. Curran
Others Present: M. Alger, S. Collins, A. Finnemore, M. Healy,
K. LaForge, J. Margeson, T. Miner, B. Riehle, D. Roeske, S. Sheldon, F.
Sinclair, R. Whitney; Media:
J. Cole,
Call to Order: 9:00 a.m. by Committee Chairman David
Pullen
BUILDINGS & GROUNDS
MAINTENANCE BUILDING:
A referral was received from the
Ways & Means Committee to consider issues related to a proposal for
construction of a
Public Works Superintendent David Roeske
summarized the
The proposed building is 4,800
square feet (40’ by 120’), and it includes a storage area, workshop, and office/meeting
room. Mr. Roeske stated that the size is
the minimum for their needs; it is not over-sized. Plans call for completion by Spring 2012. The metal
building is similar to a
The proposed site that the Public Works
Committee is looking at is the back corner of the parking lot behind the
Legislator Benson voiced his
objection to building in the back lot due to the reduction in parking spaces,
not only by the building itself, but access needed in front of it. Mr. Roeske noted that additional spaces are
being added at the side and back of the Courthouse addition. Shari Collins asked how many parking spots
would remain after construction. Mr.
Roeske responded that it’s difficult to estimate until the paving and layout
are done, but there will probably be about 40 spots left. At a future meeting, the Committee will be
discussing parking issues such as areas for employees and the public, staff who
come and go frequently during the day, and handicapped spots. Deputy County Administrator Mitchell Alger is
currently working on these issues.
Parking will improve after construction is over, and although there will
still be a need for additional space, there have been some improvements over
the past several years related to the Sheriff’s Office/Jail moving and freeing
up spaces.
Other concerns voiced about the
location were snow removal and piling snow in that back corner (it will have to be removed more often)
and possibly moving some of the storage space to another location (not convenient because deliveries would
have to be made at other spots and transported, taking time and labor; and
since storage is only one-third of the building, we wouldn’t gain that much in
parking). When asked if heated
floors were considered, Mr. Roeske replied that they didn’t look into that; the
design includes forced air heating with A/C running through the same ducts. Changing would require re-design and a new
permit, which would hold up paving, etc.
Sheriff Rick Whitney explained the
need for his staff’s continued presence in the
Legislator Benson asked about
utilization of the ground level of the Courthouse addition. Mr. Roeske explained that the entire ground level
is being used, but it wouldn’t have been adequate for maintenance, due to
noise, welding, etc. Committee Chairman
Pullen noted that originally there was some empty shell space on the ground
floor of the addition, but the Treasurer’s Office had to be re-located to allow
space for the Courthouse security area, and Information Technology and the Real
Property Tax Agency were moved as well.
Other than that, there are only utility areas. The addition does aid in complying with
regulations and code issues by providing handicapped access via the elevator connection
to the Courthouse. Mr. Pullen also noted that most of the empty
space on the second floor of the addition will now be used for the District Attorney,
opening up space for the
Chairman Crandall commented that
there were several plans with support from various legislators, with discussion
centering on location and cost, but there was not support for the plan that
came out of Public Works. They came back
and approached it in a different way and cut $300,000 from the original cost,
but aside from the cost were these other questions related to size and construction
materials. Mr. Roeske has adequately answered
each, but Chairman Crandall still questions if it’s enough of a compromise to
get support. Regarding the former Jail
space, the original bond proposal would have addressed what to do with that,
but it wasn’t supported, so now we’re picking through other space issues. In his opinion, one of the most expensive
parts of the
Legislator
Legislator Sinclair remarked that he
supports the location and the need for the
Legislator Sinclair presented the
Insulated Concrete Masonry Wall (ICMW) construction as another option. The advantage of this construction material
is that it provides a thermal mass inside the insulated barrier that holds its heated
or cooled environment longer. The
product is manufactured locally, and there are local construction
examples. Mr. Sinclair noted that he
suggested this alternative several months ago, as he felt the material could
match the feel of the campus better.
There is energy efficiency to be gained long term, as well as efficiency
in building it. The walls are already
finished. There are savings to be
realized on labor, because you’d have one mason as opposed to several workers
for another type of construction. Mr.
Sinclair gathered the following rough estimates:
Southern Tier Concrete –
4,860 block (12”), 12’
wall, 40’ by 120’, including firewall,
plus
miscellaneous materials/grout – Est.
$ 25,000
Miller & Richards –
Lay 4,860 block,
including control joints, at prevailing wage – Est.
$ 38,000
Joist system, 4/12, 42’
by 120’ – Est.
$ 6,500
Install rafters – Est.
$ 15,000
Swan Roofing –
Metal roof, including
underlay, $50/sq by 330 sq – Est. $ 16,500
Foundation – 47 cu yds @ $400/yd – Est.
$ 20,000
Floor – 178 cu yds
@ $300/yd – Est.
$ 54,000
Foam Floor Insulation – Est.
$ 6,000
TOTAL for Unfinished Shell – Est.
$181,000
Mr. Roeske commented that a lot of
things were left out, such as the contractor’s profit margin, and we wouldn’t
be guaranteed that materials would be purchased locally. The project wouldn’t be bid out in
portions. The contractor would choose
where he purchased materials. Mr. Sinclair
stated that we wouldn’t have to go with just one big contractor. This option might be more work for the
department, but we have an engineer and skilled people on staff,
and the savings are there. He explained
that this rough estimate is for construction to the same point where the other
option came in at an estimate of $355,800.
He put these figures together to address the concern of the contractor
that concrete construction would be a more expensive option. The ICMW option can save money, it fits in
with the architecture of the campus, it’s efficient, it’s
greener, and it utilizes local business.
The insulation factor is listed at R20, but adding in the thermal mass
holding it increases that efficiency.
Mr. Sinclair submitted ICMW information and his rough estimates for
consideration.
Mr. Roeske and County Attorney
Thomas Miner both commented that if we changed construction material, the
project would have to be re-bid.
Chairman Crandall questioned to what degree the design would have to be
re-done. Mr. Roeske stated that we would
have to hire an engineer to design it, because County staff doesn’t have the
time. Committee Chairman Pullen voiced
concern about the Wicks Law and working on the project with several contracts
in different stages to get it done.
Right now, the price for the shell is $355,800, but the total project
cost is about $450,000. The option Mr.
Sinclair suggested is a totally different system and would require a new design
and plans by engineers or architects before bidding, which involves more cost. On the other hand, we already have the investment
of the design costs for the steel construction proposal.
Chairman Crandall questioned what
utilities would be needed and the value of thermal efficiency in the ICMW
proposal if the function of the facility was scaled back to storage and some
shop work reducing the size of the building’s footprint. Mr. Roeske replied that they would still have
to run a gas line. They’re planning on
using the A/C units taken out of the former Information Technology Office
area. Legislator Fanton pointed out that
the building still has to have some heat.
Mr. Roeske questioned where the maintenance staff would be located. He hasn’t found an adequate space in the
Legislator Cady addressed a misconception
in the public by clarifying that the
Mr. Pullen commented that to use the
space upstairs, there would have to be elevator access. Right now, the only elevator that goes to the
top floor is in the Sheriff’s area, but that doesn’t stop at the first and
second floors. How to provide that
access is probably beyond the scope of this meeting, but if there’s a way to
save money on the
Legislator Fanton commented on the
various renovation projects Public Works has undertaken. They need office and work space. The proposal is within this years’ budget
with a little more needed next year for finish work, and now we’re going through
the third committee looking at other plans.
The County is not financially strapped at this time. The steel building may not be as fancy as a
brick building, but Public Works tried to go with the minimum to meet their
needs. Mr. Fanton questioned the “design-by-committee”
when the building has already been designed.
Also, they looked at other sites, and they weren’t practical. Maintenance staff will be working in these buildings
all the time, so it’s not practical to isolate them and spread them out.
Chairman Pullen agreed that Public Works
has been, and will be, involved in the moving and renovation for numerous
projects including District Attorney,
Location – The consensus of the
Committee was to construct the Maintenance Building in the back north corner of
the parking lot behind the County Office Building (opposed: Benson).
Chairman Pullen noted that this is the location that the Public Works
Committee decided on, and there doesn’t seem to be support for another
location. There is no perfect
solution. Legislator Graves stated that
Public Works is the “first responder” for electrical, plumbing, and ice, so it
makes sense to have the Maintenance Building as close to the worksite as
possible.
Material and Design – Chairman Pullen
pointed out the additional design expense involved with the ICMW approach
proposed by Legislator Sinclair.
Legislator
ELEVATOR ACCESS TO TOP
FLOOR OF
Committee Chairman Pullen
distributed copies of an old floor plan for the ground floor of the
Chairman Crandall remarked that
we’ve discussed use of the top floor of the
Next Meeting: Wednesday, July 6, 2011, at 3 p.m.
Adjournment: The meeting was adjourned at 11:00 a.m. following a motion made by Legislator
Graves, seconded by Legislator Fanton and carried.