COURT FACILITIES AND COUNTY SPACE NEEDS COMMITTEE

June 1, 2011

 

** NOT APPROVED **


Members Present:  D. Pullen, D. Fanton, D. Cady, K. Graves, C. Crandall;

            Absent:  G. Benson, P. Curran

           

Others Present:  M. Alger, M. Armstrong (Bovis), M. Balling (Bovis), D. Button, M. Healy, J.  Margeson, T. Miner, B. Riehle, D. Roeske, F. Sinclair, R. Starks

 

Media Present:  B. Quinn (Wellsville Daily Reporter)

 

Call to Order:  3:00 p.m. by Committee Chairman David Pullen

 

Approval of Minutes:  The minutes from the meeting of May 4, 2011, were approved following a motion made by Legislator Graves, seconded by Legislator Fanton and carried.

 

COURT FACILITIES PROJECT, CONSTRUCTION MANAGER UPDATE:  

            Mark Balling from Bovis Lend Lease presented a progress report (copy of report attached to original minutes).

 

Budget Review – Anticipated Cost Report:

            Mr. Balling reminded committee members that last month they talked about not including the costs to renovate the DMV and DA in the project so the $75,000 that was included in the contingency line item has been taken out.  Even if all contingency funds are spent, the project is still more than $2 million under budget. 

 

            They have decided not to complete Alternate #1 (see #115 below) which was to polish the brass fixtures because they appear to be in pretty good shape.  The Office of Court Administration was going to reimburse the County, and under Alternate #2, $5,000 was added back in for a net wash.

 

Change Event Log (Changes from Last Month):

 

Approved Revisions:

·         #100 – Add a Space Temperature Sensor in Janitor’s Closet 125 per CB-79  - approved at $837.02

·         #103 – Abatement of Plaster Ceilings and Re-support of Mechanical Trapeze System per RFI #0186 in lieu of Note #11 on Demo Drawings – approved at $6,738.27

·         #113 – Abatement of Pipe Insulation for Breakthrough in Corridor 107 and Disturbed Duct Tape at Locations TBD – approved at $830.67

·         #115 – Delete the Work of Alternate No. 1 – approved credit of ($5,000)

 

Approximated Revisions (Pending):

·         #082B – Future DMV Area Mech/Elect Removals for Abatement (Mr. Balling indicated that they wanted to leave the area gutted and safe so some holes were filled and some electric was disconnected – estimated at $2,000

·         #114, #116, #117 – Myriad of Issues and Field Conditions uncovered After Abatement – estimated at $25,500

·         #118 – Sanitary Piping Revisions at Toilet Room 104 per CB-92 – estimated at $1,500

·         #119 – Structural Modifications for Ground Floor Entry to Addition and at Plaster Cornice per CB-93 (Mr. Balling explained that the concrete extends all the way up to where they want to put the door, and they couldn’t have known that in advance) – estimated at $7,500

·         #120 – Fire Safe Pre-existing Floor Penetrations per CB-94 – estimated at $15,000

·         #121 – Ceiling Height Change in Room 309, Power Change in Room 117, New Window for DA in Shell Space, and Crack Infills in the Existing Courthouse Floors per CB-95 - estimated at $9,000

 

Relative to #120, Mr. Balling briefly mentioned unknown factors that will need to be looked at.  The County will need to work with Code Enforcement Officials and develop a long-term strategy for addressing these issues.  Mr. Balling and Mr. Armstrong indicated that you do not see the penetrations when the floor is in place, but they have been trying to take steps to bring the building up to code.  Committee members indicated that they do not want to do more than required unless there is a safety factor.  Mr. Balling and Mr. Armstrong will continue to work with the State Code Enforcement Officer and report back to the committee if necessary.

 

Committee members briefly discussed the ceiling mentioned in #121.  The soffits currently cover part of the windows, and they will be removed. 

 

The project is 87 percent complete, and they have used about 79 percent of the contingency.  Overall the project is about $2 million under budget.  Legislator Don Cady asked what happens to any remaining contingency funds when the project is complete.  Mr. Margeson indicated that it would fall to the surplus of the project, and based on conversations Mr. Margeson has had with bond counsel, it can be used to make debt service payments until it has been exhausted.  It was also noted that the money can be used for a project specifically associated with the construction project.  Chairman Curtis Crandall noted that there are some people who appear to be confused about the cost of this project, and it would be worthwhile to prepare a financial update.  Court Facilities and County Space Needs Committee Chairman David Pullen indicated that he would prepare something and run it by Chairman Crandall and County Administrator Margeson.  Legislator Pullen stated that we were facing a much different scenario than when we started looking at the project with estimated costs approaching $30 million.  Our project ended up coming in around $14 million, and we have $2+ million in contingency.  The news could have been much worse.

 

Legislator Dwight Fanton thanked the representatives from Bovis for their attention to the project and coordination with the Public Works Department.  Mr. Balling noted that the contractor has not come to them regarding any work extensions.  They are projecting an early September completion date.

 

Site Overview – Safety Report

            No safety warnings issued during the past month.  Bovis Lend Lease has conducted 254 safety orientations through June 1, 2011.  Seventeen written safety notices have been issued since the beginning of the project.  There have not been any lost-time incidents for the project.

 

Work Performed in the Past Month (May):

·         Phase II punch list ongoing (mainly millwork corrections)

·         Late Phase II change events ongoing

·         Asbestos abatement completed on Second and Main Floor with Ground vestibule underway (They had quite a few abatement changes, and they are running a little behind schedule.  They may try to make up some time, and they should know in a few weeks.)

·         Asbestos abatement air monitoring ongoing

·         Demolition completed on all floors

·         Metal studs completed on all floors

·         Insulation installed on Second Floor

·         Drywall underway on Second, Main and Ground floors

·         Drywall finishing underway

·         Demolition of breakthrough at Ground Floor underway

·         Electrical rough-in underway on all floors

·         HVAC control valves completed in crawl space

·         Plumbing rough-in completed on Second Floor

·         SWPPP fencing and inspections (Storm Water Pollution Protection Plan)

 

Sixty-Day Look Ahead (June and July):

  • Phase II millwork corrections completed
  • Phase II changes completed
  • Asbestos abatement and air monitoring completed on all floors
  • Drywall finishing completed on all floors
  • HVAC, plumbing and electrical completed on all floors
  • Painting, ceramic tile and ceiling grid completed
  • Light fixtures completed
  • Floor finishes completed
  • Millwork completed
  • Handicap lift installed on Ground Floor
  • SWPPP fencing and inspections (Storm Water Pollution Protection Plan)

 

Probation Director Robert Starks asked if the Ground Floor exit would be available soon, and Mr. Armstrong indicated that it should be ready in about two weeks.

 

DMV AND DISTRICT ATTORNEY’S OFFICE SPACE

            Public Works Superintendent David Roeske stated that Public Works Department employees will be completing the District Attorney’s Office space, and they hope to have it done by the end of the project.  The DMV space will be a little more difficult, and they have not developed a timetable yet.

 

PROBATION DEPARTMENT SPACE

            Probation Director Robert Starks distributed copies of the existing floor plan for the Probation Department and surrounding areas.  Mr. Starks noted that because of code restrictions and load-bearing walls, there is not a lot that they are going to be able to do.  Mr. Starks and committee members discussed the floor plan and some possible renovations including the removal of certain bathrooms.  Mr. Starks indicated that he will be meeting with someone next week to talk about the possibility of installing a high-density filing system. 

 

Once the DMV is relocated, the Probation Department is hoping they may be able to use the County Clerk’s storage space.  Several people in attendance believe the storage area is used for license plates.  Legislator Pullen indicated that he would like to do an inspection of the storage area so he can understand exactly what the usage is.  Legislator Pullen noted that the County Clerk’s break room space seems to be very generous and suggested that it could be shared with the Probation Department.  There was also a discussion about the public and staff bathrooms and whether or not those bathrooms actually need to be separate.

 

COUNTY HISTORIAN SPACE

            Planning & Economic Development Committee Chairman Fred Sinclair indicated that he has not had further discussions with the County Historian Craig Braack about the possibility of relocating to the Support Collection Building.  Committee members discussed moving some of the agencies currently located in the Cooperative Extension Building to the Support Collection Building as the Historian should not need the entire building.  Committee members mentioned wanting to use the basement of the building for storage, but agreed that it is very damp, and additional work would need to be completed first.  Legislator Dwight Fanton suggested they might want to consider using a raised floor and installing a sump pump in conjunction with a dehumidifier.  Committee members requested the Clerk of the Board to ask the County Historian to attend the next meeting so that further discussion can take place.

 

PARKING PLAN

            Deputy County Administrator Mitch Alger distributed copies of a Departmental Parking Survey that he completed after meeting with the various departments.  After Committee Chairman David Pullen shared some concerns regarding the parking spaces needed, Mr. Alger clarified that he prepared the document based on maximum potential.  The Departments highlighted in grey are housed offsite.  The survey was prepared to give committee members an idea of what they should be shooting for in terms of parking capacity.  Committee members requested Mr. Alger to work with the departments to determine how many customers are passing through in a day.  Although the numbers can vary widely depending on what’s going on, we need to have some idea of how many public users we need to provide for.  Refer to Deputy County Administrator

 

            Committee members briefly talked about the possibility of using some of the property on Court Street for parking.  No scaling has been prepared, but they would like to determine how many cars can be accommodated on Court Street.  Committee Chairman Pullen commented that the state keeps demanding that we need to do more and more, and ultimately we could use all of Court Street.  We are currently paying $500/month to use the church parking lot off of Court Street. Committee Chairman Pullen also talked about the possibility of installing a roadway behind the new building and creating additional spots there and by the Veterans’ Memorial.   Committee members would like to determine how many parking spaces we currently have, and how many we really need. 

  

Next Meeting:            Wednesday, July 6, 2011, at 3 p.m.

 

Adjournment:            The meeting was adjourned at 4:35 p.m. following a motion made by Legislator Fanton, seconded by Legislator Graves and carried.

 

 

Respectfully submitted,

Brenda Rigby Riehle, Clerk of the Board

Allegany County Board of Legislators