COURT FACILITIES AND COUNTY SPACE NEEDS COMMITTEE

SEPTEMBER 1, 2010

 

** NOT APPROVED **


Members Present:  D. Pullen, D. Fanton, G. Benson, D. Cady, C. Crandall; 

            (Absent:  P. Curran, D. Russo)

 

Others Present:  M. Alger, M. Armstrong (Bovis), D. Button, R. Christman, A. Finnemore, M. Healy, J. Margeson, T. Miner, T. Parker, B. Riehle, D. Roeske, T. Ross, F. Sinclair

     

Call to Order:  3:00 p.m. by Committee Chairman David Pullen

 

Approval of Minutes:  The minutes of August 4, 2010, were approved following a motion made by Legislator Fanton, seconded by Legislator Benson and carried.

 

COURT FACILITIES PROJECT, CONSTRUCTION MANAGER UPDATE:  

 

            Mark Armstrong from Bovis Lend Lease presented a progress report (copy of report attached to original minutes).

 

Budget Review – Anticipated Cost Report:

 

            Mark Armstrong reported that there are no major changes since last month’s report.  Through the end of July, the project is at 30 percent completion for construction, and they’ve only allocated 5.3 percent to construction contingency, which equals about 0.42 percent of Javen’s base bid.

 

Change Event Log:

 

            Changes from last month’s report include the following:

 

·         #33 – Paving, Sidewalks and Curb Revision – at the County’s request, Bovis is going to ask for a price to delete all paving and related work.  Within that same change order, they are also asking Javen for a price for redoing sidewalks and curb resetting between the Courthouse and the County Office Building.  Mr. Fanton noted that we’ll be saving by not paving the back lot until all work is done, including the possible new maintenance building.  Estimated credit of ($89,000).

·         #34 – Revisions to Window and Counter in Room 229 and 230 – counter-height window for receptionist (raise the counter/lower the window).  Estimated $750.

·         #35 – Door Hardware Changes – brought about by an RFI question.  Estimated $1,200.

·         #36 – Wall Revision to Vault Room 129 – has to be a fire-rated wall.  Estimated $2,500.

·         #37 – Abatement of NW Corner of Courthouse Ground Floor and Installation of Door Opening 120A During Phase 2 – it was originally written as doing some abatement work early to gain access from the existing Courthouse to the addition.  Bovis believes they can do a temporary opening without the abatement.  Estimated $10,000.  (A good share of that cost will be eliminated.)

·         #38 – Security Addition – camera in elevator #2, intercom and distress button in the staff corridor, and duress button at DMV and County Clerk counter.  Estimated $7,500.

·         #39 – Glazing, Signage and Roller Shade Revisions (Security Addition) – for mirrored film on window of control room, signage at door 202 for emergency exit only, and window shades at  Chief Clerk Surrogate’s Office. Estimated $800.

·         #40 – Revise Door Hardware at Door 202A (Security Addition) – a new doorway that will be installed in the entrance of Courthouse, with alarm system.  Estimated $1,200.

 

Change Order Summary Report:

 

            No real changes.

 

Allocated Allowance Summary:

 

            The wireless duress system may not be used, so we may be gaining the estimated $5,000 as a credit.

 

Site Overview – Safety Report:

 

            Bovis held a Safety Stand Down on August 6 to further communicate the importance of safety to the workforce.  There were four safety warnings issued during this reporting period for improper ladder use and lack of fall protection.  On August 16, there was an OSHA site inspection, and one construction company was cited for improper tying off (fall protection).  Seventeen written safety notices have been issued since the beginning of the project.  There were no lost time incidents for the project to date.

 

Work Performed in the Past Month:

 

            The following work was conducted during this reporting period (progress photos included):

 

·       Installation of roof system underway

·       Stair Tower S04 completed with stairs and rails installed

·       Elevator E02 masonry completed

·       Fire protection sprinkler system underway

·       Exterior metal stud framing completed

·       Exterior sheathing underway

·       Roof joists and metal decking completed

·       SWPPP (Storm Water Pollution Protection Plan) fencing and inspections

·       Exterior brick facing underway

·       Interior metal stud partitions underway

·       Interior electrical, HVAC, and plumbing work underway

 

Sixty-Day Look Ahead (September and October):

 

            The following list provides an idea of what’s scheduled, and Bovis’ report included start and finish dates they are hoping to maintain for each activity. 

 

·         Completion of roof framing and decking

·         Completion of roofing system

·         Completion of exterior wall framing, sheathing, and face brick

·         Installation of concrete pads for dumpster and generator

·         Completion of HVAC piping and ductwork

·         Completion of sprinkler piping

·         Completion of electrical rough-in

·         Completion of interior metal studs

·         Elevator installation underway

·         Completion of window installation

·         Drywall installation underway

·         Tape and finish of drywall underway

·         Completion of exterior wall insulation

 

Mock-Up of Judge’s Bench:

 

            Mark Armstrong and Committee Chairman David Pullen reported that the first mock-up of the Judge’s bench was held last Thursday (August 26), and it didn’t go well.  The contractor was not ready despite having been reminded repeatedly.  A lot of people, including representatives from OCA, made an effort to be present for the bench mock-up to see how things would be structured and how they would affect sightlines and interactions.  It was a very important milestone.  What the contractor had done wasn’t acceptable and was very incomplete.  The Judge’s bench mock-up has been rescheduled for September 14.  The contractor has been told that this doesn’t change scheduled completion dates.  Mr. Armstrong noted that they had a meeting with the contractor to go over everything again that needs to be done for the mock-up, and they are being pushed to have it done a week ahead of time.

 

Scheduling and Timeline:

 

            Mr. Pullen questioned where we stand on scheduling.  Mr. Armstrong stated that they are addressing the concern on scheduling with Javen, and Javen has committed verbally that they will make the February 3 move-in date.  They will be held to that date, as it’s not optional.  In reviewing the schedule, Mr. Armstrong has seen where they are compressing some of the contractors’ work schedules almost unrealistically.  He and Mr. Balling will address that with them tomorrow.

 

SPACE NEEDS STUDY UPDATE:

 

            Deputy County Administrator Mitch Alger provided an update on the progress being made in talking with Department Heads and others regarding space needs in order to come up with a report.  He met first with the Department of Social Services, because they have the biggest space problem.  They are probably going to try to identify their needs first and proceed from there.  County Administrator John Margeson noted that they are relying on some work already done by LaBella Associates.

 

            Mr. Pullen relayed questions that have been raised on whether there is any “slack” space left in the Courthouse addition.  Originally there was considerable shell space on the ground floor, but when County Office Building renovations were removed from the plan, it was decided to move Support Collection into the space currently occupied by Information Technology and Real Property Tax in the basement of the existing Courthouse, and IT and RPT will move into the ground floor of the addition, utilizing all of the remaining space. 

 

            Mr. Fanton questioned the small shell space on the top floor of the addition.  Mr. Margeson replied that it was a small room to the right, near the ramped hallway into the addition, with the only access at the far end.  It’s slated to be used for storage.  Mr. Pullen asked Committee members to consider the feasibility of requesting that LaBella work up an estimate for a change order to create access to that area from the existing Courthouse in what will become the visiting Judge’s chambers in order to provide a secure route to the court rooms.  It would require another opening similar to the hallway entrance to the addition, but smaller, with a fire door and a ramp to accommodate the different floor levels.  It would be cheaper to make the change now, and it would make the area more useable.  The work wouldn’t be done until February, so there’s plenty of time to work up an estimate and make a decision.  OCA is not pushing for this, and they are aware of, and have signed off on, the fact that the only access from the visiting Judge’s chambers is down the common hallway, and the Judge will have to be escorted.  It was the consensus of the Committee to authorize the County Administrator to request that LaBella work up an estimate for the above-mentioned work.

 

Next Meeting:           Wednesday, October 6, 2010, at 3 p.m.

 

Adjournment: The meeting was adjourned at 3:35 p.m. following a motion made by Legislator Benson, seconded by Legislator Cady and carried.