COURT FACILITIES AND COUNTY SPACE NEEDS COMMITTEE

OCTOBER 7, 2009

 

** NOT APPROVED **


 

Members Present:  D. Pullen, G. Benson, D. Fanton, T. Hopkins, C. Crandall;  (Absent: W. Hall, T. O'Grady)

 

Others Present:  D. Burdick, W. Dibble, A. Finnemore, M. Kukuvka and P. Mashtare (LaBella Associates), J. Margeson, T. Miner, N. Ungermann;  Media:  B. Quinn, Wellsville Daily Reporter

 

Call to Order:  4 p.m. by Committee Chairman David Pullen.

 

Approval of Minutes: 

 

            The minutes of September 2, 2009, were approved following a motion made by Legislator Hopkins, seconded by Legislator Fanton and carried.

 

            The minutes of the special meeting on September 14, 2009, were approved following a motion made by Legislator Fanton, seconded by Legislator Benson and carried.

 

            The minutes of the special meeting on September 28, 2009, were approved following a motion made by Legislator Hopkins, seconded by Legislator Fanton and carried.

 

Court Facilities Project Estimate Update – LaBella Associates:

 

            Mark Kukuvka, from LaBella Associates, provided committee members with their latest budget estimate for the Court Facilities Project, which is at the construction document phase, or what Mr. Kukuvka referred to as the “80 percent” estimate.  The previous estimate was for the design/development phase.  (Copy of handout attached to original minutes.)  Two summary sheets were included, the first for the base project, and the second for project costs with additional scope.  Items that Mr. Kukuvka highlighted for each section were:

 

Base Project Costs: (completed as a benchmark for what the Legislature approved, does not include Treasurer, Information Technology, or Real Property Tax spaces)

 

Construction Basic Costs -

·         Construction costs are separated out for addition and renovation.

·         Design contingency has been lowered from five to one percent, due to the documents being more complete at this stage. 

·         Projected construction cost on bid day is estimated to be in the $12 million range.

 

Consultants and Miscellaneous Costs (Soft Costs) -

·         Architect/Engineer hard and soft costs, other related project costs, such as geotechnical – many of these have not changed from the previous estimate.  There are still some items that the County needs to finalize.

 

Owner Costs -

·         Allowances that have been included:  miscellaneous owner costs at $200,000, and the owner general contingency was lowered a little to $100,000. 

 

Total Projected Base Project Costs - $13.786 million, or just slightly under budget. 

 

Project Costs with Additional Scope: (ground floor finished shell space and ground floor renovation, including space for Treasurer, IT, Real Property Tax, and DSS)

 

Construction Basic Costs -

·         Design contingency has been lowered from five to one percent, due to the documents being more complete at this stage.

·         Projected construction cost on bid day is estimated to be $12.7 million.

 

Consultants and Miscellaneous Costs (Soft Costs) -

·         Remaining soft costs are very similar.

 

Owner Costs -

·         Contingencies have been adjusted and allowances were pointed out as before.

 

Total Projected Project Costs with Additional Scope - $14.5 million, or about $700,000 over what the Legislature approved for bonding. 

 

            Mr. Kukuvka noted that the remainder of the handout contains a detailed breakdown (Bovis Lend Lease was hired by LaBella to prepare the estimates).  The sections are broken down into new addition and renovation costs for each of the major trade areas (general construction, electrical, mechanical, and plumbing).  From the base project, LaBella worked hard with OCA and the County to stay within the initial budget.

 

Bid Alternates:

 

            Mark Kukuva and Penny Mashtare presented information on several bid alternates (handout attached to original minutes).  These alternates are additional items LaBella will be asking the contractors to provide break-out prices for in the event that money is available.  When the bids come in, LaBella will review the alternates and make recommendations to the committee.  OCA may want to be present, because the first four items were additional things that they wanted, and they may be able to provide funding for them.  The six alternates include:

 

1.      Polish Brass Light Fixtures (in existing Ornamental Courtroom and Law Library)

2.      Light Fixture Removal/Replacement (in existing Hearing Room, replace with pendant lighting)

3.      Strip and Refinish Pew Seating & Jury Box Seating (existing Ornamental Courtroom)

4.      Enlarge Existing Ornamental Courtroom Bench (clerk's counter space)

5.      Replace Existing Fan Coil 3-Way Control Valves with 2-Way Control and Add VFD Pumping (in existing Courthouse building, also remove existing circulating pump motors, replace with Inverter duty rated motors and variable speed drives)

6.      Solid Surface Lavatory Two Station (in lieu of base bid required laminate counter with two porcelain sinks in public restrooms)

 

            Alternate No. 5, the heating unit, may result in some energy savings.  When this was reviewed previously, the payback period was not that great (seven to ten years), but there is more energy efficiency.  The cost estimate for the heating unit was somewhere between $70,000 and $100,000.  Alternate No. 6, solid surface lavatories in the public restrooms, would be more durable for the higher level of use.

 


Draft Project Schedule:

 

            Mr. Kukuvka and Ms. Mashtare presented a draft project schedule, which has also been bound into the bidding documents for the contractors.  The handout included the following:

 

Start            Finish            Task

10/06/09          01/05/10          BID PHASE

10/06/09          10/08/09          CD Documents to Print & Code Enforcement for Building Permit

10/05/09          10/07/09          Advertise for Bid

10/08/09          11/12/09          Contractor Bidding Period

11/12/09          11/12/09          Bids Due

11/13/09          11/19/09          Bid Review & Recommendation to Legislature

11/20/09          12/08/09          Legislature Bid Awards

12/08/09          01/05/10          Fully Execute Contract

12/08/09          01/05/10          Bond & Insurance

01/05/10          01/05/10          Contractor Notice to Proceed

01/05/10          06/24/11          CONSTRUCTION

01/05/10          02/10/10          Mobilize on Site

01/19/10          04/12/10          Shop Drawings & Submittals

01/05/10          12/27/11          COURTHOUSE ADDITION

03/02/10          05/03/10          Foundations

03/02/10          03/31/10          Structure

04/01/10          08/18/10          Building Envelope

04/01/10          08/30/10          MEP Rough In

08/19/10          09/23/10          Interior Framing and Partitions

09/25/10          12/27/10          Finishes

11/27/10          12/27/10          Punch List

12/27/10          01/05/11          Move In Period

01/05/11          06/24/11          EXISTING COURTHOUSE RENOVATIONS

01/05/11          02/08/11          Demolition

02/09/11          03/11/11          New Framing & Partitions

02/19/11          04/11/11          MEP Rough In

04/04/11          06/20/11          Finishes

05/24/11          06/24/11          Punch List

05/24/11          06/24/11          Site Work Completions

06/25/11          06/30/11          Move In Period

 

            Ms. Mashtare highlighted the following points.  Bidding documents will be available to contractors October 8, with bids due back November 12.  A pre-construction bidders' walk-through is scheduled for October 22 at 10 a.m.  Bids will be opened here on November 12, in the Legislative Chambers, at 2 p.m.  LaBella will have a week for bid review and recommendations, then awarding of bids will take place between late November and early December.  Execution of contracts and bonding will occur between December 8 and January 5, 2010, with notice to proceed on January 5.  There is a twelve-month period of time for construction of the addition, with a built-in "move in" period suggested by the Courts for the period between Christmas and New Year's when they typically close down.  Renovations will begin January 5, 2011.  Job completion is planned for June 30, 2011. This schedule has been put into the bid specifications after the summary of work as a guideline for the contractor.  We are looking at 535 days of construction.

 

            Legislator Fanton expressed concern about beginning the project in January.  Mr. Kukuvka noted that this project lends itself well to that.  There are shop drawings, lead time for materials, site prep, demolition, mobilization, setting up temporary power - things they can do in cold weather.  It helps them to have that time because three months are needed for shop drawings; if they can use that three months to correct any coordination issues, then as soon as spring breaks, they can hit the ground running.  Foundations will be going in between March and May.

 

            Mr. Kukuvka commented that in order to stimulate interest in the bidding market place, bid documents will be scanned onto a website to allow view-only access by sub-contractors prior to purchasing.  They can also view the plan-holder list, making it easier for them to make contacts.  Mr. Kukuvka noted that the PLA, including all signatures, has been bound into the bidding document.  Contractors will be aware of the PLA and that we are looking for a single prime contractor.

 

            Legislator Benson questioned the January 5 date for execution of contract, as a new Board will be in place on that date.  Mr. Kukuvka replied that the legislative award of bids will take place at a Board meeting sometime between late November and early December; the rest is administrative with the County Attorney, just a procedural matter.

 

            Mr. Kukuvka suggested that the committee may want a special meeting with LaBella prior to Board consideration of bids.  The first Board meeting in December is the 14th, so the committee could meet on December 2 to hear LaBella's recommendations on contract bids.

 

Construction Management / Clerk of the Works Services:

 

            Mr. Pullen noted that proposals for Construction Management and Clerk of the Works services have been reviewed and interviews were held.  We are at the point where we need to decide how to proceed.  Discussion was held at the committee meeting on September 28, at which time Mr. Pullen stated he felt it was to our advantage, although not the cheapest option, to retain the services of a Construction Manager.  A decision needs to be made so that whoever is retained can be involved in reviewing the bids when they are received.

 

Executive Session:

 

            A motion was made by Legislator Fanton, seconded by Legislator Benson and carried to enter into executive session to discuss the performance history of particular corporations.  Following discussion, a motion was made by Legislator Fanton, seconded by Legislator Hopkins and carried to end the executive session and return to the regular meeting.

 

            No action was taken on the retention of a Construction Management firm, but the issue will be considered at a special meeting of the committee on Tuesday, October 13, at 1:30 p.m.

 

 

Next Meetings:         Special meeting, Tuesday, October 13, 2009, 1:30 p.m.

                                    Regular meeting, Wednesday, November 4, 2009, 4 p.m.

 

Adjournment:  The meeting was adjourned at 4:55 p.m. following a motion made by Legislator Fanton, seconded by Legislator Hopkins and carried.

 

Respectfully submitted by

Adele Finnemore, Journal Clerk