COURT FACILITIES AND COUNTY SPACE NEEDS COMMITTEE

JUNE 4, 2008

 

** NOT APPROVED **


Members Present:  D. Pullen, W. Hall, G. Benson, D. Fanton, T. Hopkins, T. O’Grady, C. Crandall

 

Others Present:  J. Carminati, L. Ballengee, W. Dibble, W. Emerson, A. Finnemore, J. Foels, A. Isenberg, B. Kelley, P. Fogarty, K. Kruger, M. Kukuvka, J. Margeson, P. Mashtare, B. Riehle, T. Ross, K. Toot, N. Ungermann;  Media:  B. Quinn, Wellsville Daily Reporter

 

Call to Order:  3:00 p.m. by Committee Chairman David Pullen.

 

Approval of Minutes:  The minutes of May 7, 2008 were approved following a motion made by Mr. O’Grady, seconded by Mr. Fanton and carried.

 

LaBella Update on Courthouse Addition and County Office Building Renovations:

(Penny Mashtare, Mark Kukuvka)

 

Review of County Office Building (COB) Renovations:

 

            Penny Mashtare, from LaBella Associates, reported on the latest revision of the County Office Building renovations, including furniture layout, following her review of the floor plans with departments on May 30.  Areas will be filled in with as little demolition as possible, making use of existing spaces and walls when feasible.  (Updated floor plans attached to original minutes).  A summary of the floor plans includes:

 

Ground Floor:  Health Department will occupy most of the floor; WIC and Cancer Services will be brought back in from off-site; Health reception will be near the entrance, allowing for better direction of customer flow; Public Defender’s Office stays where it is; Maintenance will have the Sally port area.  A suggestion was made to locate the entrance door for the Public Defender’s Office in the hallway, rather than in the former Sheriff’s area.  It was later noted that a second door out of the Public Defender’s Office would be better for security, instead of just relocating the door.  Better signage was suggested, possibly color coded, to help with directing customers.

 

First Floor:  Social Services will have the entire floor; Child Support Unit will be brought in from off-site (records stored in the basement of the Support Unit building will be out-sourced).  Existing work stations and exam rooms will be taken advantage of, and acoustics will be addressed with partitions to help with noise and privacy.  Storage was addressed: high density storage area is the same, and there is a file room, but a lot of the filing goes with personnel into offices; archival records will be out-sourced.

 

Second Floor:  Social Services will occupy nearly half of the floor.  The present Legislative Chambers area will require the most work on this floor, requiring new walls to section it off.  Public Works remains and will expand in area.  Information Technology will move up and acquire additional storage space.

 

Third Floor (former Jail):  This floor will require the most work.  Legislative Board Clerk’s Offices, Caucus Room, and Chambers (from a load bearing/code standpoint, the Chambers had to be located in the former outdoor rec area); District Attorney; County Attorney; County Administrator; Human Resources; Workers’ Compensation (in the HR area, from off-site); mail/copy room.  The need for the corridor at the back of the Chambers area was discussed, as was the possibility of reversing the direction of the Chambers.  Mr. O’Grady questioned if all the conference rooms were needed, and if one of those areas could be used to bring the Youth/DWI Office back in from off-site.  Ms. Mashtare noted that there are still some unassigned spaces that could be looked at.  Mr. Isenberg asked if doubling for Grand Jury was discussed when planning space for the Legislative Chambers and when meeting with the District Attorney.  Mr. Kukuvka responded that it was accommodated for.

 

Courthouse Basement/Addition Ground Floor:  Board of Elections will be brought back up from off-site and voting booths will be out-sourced; County Treasurer will be moving into the addition ground floor immediately off the main elevator lobby area (present Treasurer’s Office will be the queuing area for building security).  The possibility of storing voting machines in the unassigned space on the addition ground floor was discussed.

 

            Mr. Fanton questioned where the rest of building maintenance would go following the removal of the large building out back.  They have some space in the former Sally port, but due to noise, it might not be appropriate to go in the unassigned space on the ground floor of the addition.  Mr. Kukuvka noted that the ground floor unassigned space is tentatively slated for storage; it’s unfinished space right now to help with keeping costs down.  If the County wants that built out to a certain level, he will need to know that.

 

            With the Support Unit moving into the main building, a decision will have to be made on what to do with the vacant building.

 

Overview of Demolition Plans and General Approach for COB Remodeling:

 

            Ms. Mashtare and Mr. Kukuvka displayed demolition plans which Ciminelli will use to estimate costs.  A mechanical team will be coming in next week for analysis and assessment.  Guidance will be needed from this committee on the level of renovations and finishing work the County will want in order to ascertain proper estimates.  LaBella previously supplied estimates for three different levels of renovation, from “scrape and paint” on the lowest level; to some walls, carpeting, and tile; to a more major level, as on the third floor where nearly everything will be new.  When the drawings are given to the estimator, a narrative will be included to ensure basic finishes, but they need direction on what to include in the narrative such as how much electrical renovation is needed, number of data drops, etc.  Discussion included ceilings, flooring, existing lighting, and hardware.  What can be salvaged will be, to keep the project as economical as possible.  There will be a lot of judgment calls, but these issues affect pricing.  Mr. Kukuvka noted he realized the legislators would not know what all the needs would be, but is looking more for an attitude, such as whether to paint all rooms, and leaving flooring if it is in good condition, or fixing it if tiles are missing.

 

Next Steps:

 

            Mr. Kukuvka suggested the committee review the latest floor plan revisions and forward comments back to him through Mr. Margeson within one week.  LaBella’s next step will be to write up the narratives and give the information, along with the mechanical team’s figures, to the estimators.  Estimates will be presented to the committee at the July meeting.  If the committee approves the figures, LaBella can be ready for a presentation to the full Board of Legislators on July 14.  Mr. Crandall will schedule a Committee of the Whole meeting on July 14 following the Board meeting at approximately 3 p.m.

 

Preparation for Office of Court Administration (OCA) Meeting on June 10:

 

            Mr. Margeson reported that he, Mr. Kukuvka, and Ms. Mashtare will meet with OCA officials on June 10 to review the Courthouse addition project and go through the floor plans floor by floor.  LaBella will take the plans, elevations, the comparison space program (which is a strong selling point in reducing the size of the addition), and a three-dimensional piece. It was noted that the County Office Building third floor drawing should be taken to show the District Attorney area and Grand Jury flex space.  The County’s proposed Capital Facilities Plan will be presented to obtain OCA’s feedback.  Mr. Isenberg noted that the County needed to complete some of the items that were included on LaBella’s draft capital plan letter, such as benchmarks, etc. in preparation for the June 10 meeting.  Mr. Pullen noted that some of these dates are already known, so they can be included.  Mr. Kukuvka requested he be notified if LaBella needed to expand on any of their information.

 

            Mr. O’Grady suggested that another informational pamphlet be prepared following the June 10 OCA meeting in order to keep the public informed of progress on the project.

 

            Mr. Isenberg reported that after OCA’s Ed Rodman was in town for a meeting with LaBella on the revised floor plans, he met with the Judges, and with some minor tweaking, everyone on the Court side is on board with the plan.

 

New York State Energy Research and Development Authority (NYSERDA) Information:

 

            Mr. Pullen reported that Legislator Dibble provided him with information from NYSERDA regarding state funding availability for new construction programs adhering to “green” guidelines for energy efficiency, performance, and energy consumption.  Mr. Kukuvka remarked that a lot of county projects have applied for NYSERDA incentives, some more aggressively than others.  Sometimes you have to put in more expensive units in order to reap some money back, but you certainly wouldn’t get the difference in costs back.  Mr. Kukuvka stated it makes sense to apply.  The process involves getting the project registered, a case number would be assigned, and a technical assistance person would work with LaBella on how much to go for. 

 

            Mr. Isenberg commented that the County should be working with any agency appropriate at the state level for any incentives that are available.  OCA provides assistance with a portion of the interest on bonding.  NYSERDA would be pursued independently by the County, not through OCA.

 

            Mr. Pullen noted that the project could cost more up front, with pay back in energy savings over the life of the bond.  The County’s goal was to keep upfront costs as low as possible, but this might be something to consider with energy costs what they are.  Mr. Hopkins commented that if we’re talking of using something that’s proven as an energy saver, we’d know the savings up front, but he wouldn’t want to use something that’s unproven.  Mr. Kukuvka remarked that “more aggressive” just means more sophisticated technology, as in higher efficiency furnaces.  You’d be spending more but the NYSERDA incentive would also be higher.  NYSERDA can do a third-party calculation to determine the payback period.  Mr. Kukuvka’s experience has shown that most counties have pursued the incentive casually, only a few aggressively.  He will refer it to their engineers in light of higher fuel costs and get a fresh look at the payback period.  There is also a green building movement independent of NYSERDA that involves the use of recycled materials, etc.  The US Green Building Council has a Leadership in Energy and Environmental Design (LEED) Certified Program.  It costs five to ten percent more up front to construct a completely LEED Certified building, for which you would reap benefits in energy savings over a period of years, although there are no incentives.  Mr. Kukuvka noted that this project has not been priced yet as a green building, but we can still be good stewards as far as some things go without getting LEED certified.  Mr. Hall stated there is no chance now to do a completely green building, and it’s too expensive.  Mr. Pullen commented that we don’t lose anything by registering with NYSERDA.  Mr. Kukuvka will register the project with NYSERDA and check with LaBella’s engineers on how aggressively to pursue those incentives.  He will report at the next meeting.

 

Space Options for Office for the Aging/NY Connects/Veterans’ Services:

 

Former Belmont School:  (County Administrator John Margeson)

 

            Mr. Margeson spoke with Ray DeTine from the Belmont Betterment Association approximately two weeks ago and discussed the County’s interest in space, what it would be used for, and what would be needed.  Mr. DeTine wanted to speak with an investor.  Mr. Margeson is waiting to hear back and will contact Mr. DeTine later this week.

 

Crossroads Center:  (Industrial Development Agency Executive Director John Foels)

 

            Mr. Foels, along with Waterbourne Construction Advisor James Carminati, presented preliminary lease figures and construction estimates for a 6,000 sf facility on the Crossroads Center property.  (Space needs were estimated at 5,400 sf; the 6,000 sf allows room for expansion.)  The IDA approached this project by looking at the costs prior to design.  The options for lease, costs of construction, and design were made with the assumption that construction would be in keeping with the specifications and level of construction of the present building with some upgrades.  Handouts were distributed (copy attached to original minutes).  Two lease term options were included:

 

10-year initial lease term rate (based on a fifteen-year loan):

Years 1-5

$11.59 psf

 

Years 6-10

$12.75 psf

                                Two additional five-year renewal terms:

Years 11-15

$14.03 psf

 

Years 16-20

$15.43 psf

 

 

 

15-year initial lease term rate (based on a twenty-year loan):

Years 1-5

$ 9.92 psf

 

Years 6-10

$10.91 psf

 

Years 11-15

$12.00 psf

                                Two additional five-year renewal terms:

Years 16-20

$13.20 psf

 

Years 21-25

$14.52 psf

 

The rental rate is based on this being a financed project.  The rate secured on the existing building is six percent, and Mr. Foels expects those numbers will be the same.  The estimates included the entire cost of the project and amortization over those time periods, an additional five percent for structural maintenance, five percent management fee required by the banks, and three percent for soft costs.  The IDA will own the building (tax exempt).  Estimates and cost breakdowns are based on assumptions on square footage, keeping like specifications, and upgrades, and there may still be some economies.  The next step will be working on floor plans and specifics.  The total cost estimate for actual construction was $588,865.

 

Construction of Metal Building Adjacent to the County Jail:

 

            Mr. Margeson distributed a handout prepared in concert with Public Works Superintendent David Roeske which provides a rough estimate for construction of a 5,400 sf metal building adjacent to the County Jail.  A Silver Creek, NY company provided DPW with a quote of $72,700, or $30.29 psf, for a 2,400 sf pre-engineered metal building.  Using the same cost per square foot, a 5,400 sf building would cost $163,566 (inside unfinished, and excluding footers and foundation).  Additional work required in the construction, including foundation, footer, interior finishing, utilities, site work, septic system, exterior painting, eaves, and landscaping, is roughly estimated at $232,000, bringing the cost to purchase and erect this building for occupancy to $380,000 to $400,000.  Since the County will own this building, annual operating expenses, such as insurance, utility bills, maintenance/cleaning, etc., have been estimated at $20,000 to $25,000 per year.  Debt service on a $400,000 building with a ten-year amortization would be approximately $44,000 per year.

 

            Mr. Ungermann felt that the figures provided were close.  He noted that the metal buildings can be built with an expandable end wall, so they can be added on to at minimal cost.  There is a lot of room at that site (23 acres remain).  We could solve our storage space problems as well, and storage space isn’t as expensive as office space finishing.

 

Other Space Options:

 

            Mr. Pullen made note of communications forwarded by Office for the Aging Director Kimberley Toot which were received from other property owners in the area (Back in Thyme, south of Belmont; and Boomers, in Scio) wishing to have their properties be considered for County space needs.

 

Next Steps / Discussion:

 

            Mr. Foels would like to come back to the committee and look at tightening up their estimates and look at floor plans.  Mr. Ungermann questioned why the IDA couldn’t build and provide rental space at the Jail site.  Mr. Foels responded that the IDA should have ownership of the property, but that he would have to check to see how that would work.  Mr. Fanton pointed out that if the IDA constructs the building, they don’t have to meet the same labor laws, whereas the County would presumably be working through a private contracting firm.  With a $200,000 difference in costs, where is the benefit in the IDA project?  Mr. Foels noted that the steel structure is a good option with cost benefits, but the projects are two different construction issues.  The IDA couldn’t construct a metal building at the Crossroads site because it wouldn’t “fit” there.

 

            Mr. Carminati commented that the construction numbers were probably close on the pre-engineered building.  IDA numbers were based on using structure standards in the existing building.  If the County has a budget, they can work with us to try to stay within that budget by changing some things around.  Mr. Hopkins noted he would like to see pictures and actual costs.  Mr. Pullen commented that the proposals are different in ownership, financing, etc., and suggested investigation into the feasibility of the IDA building on another location.  Mr. Ungermann remarked that in looking at other sites, accessibility and sight distance are important considerations.  The Jail site has more sight distance in both directions than the Crossroads site.

 

            Chairman Crandall stated that we’re not comparing like issues.  We have to look at annual costs if moving in a different direction than the IDA project.  We have to look at the pros and cons of each proposal.  Chairman Crandall reminded the committee of the presentation regarding coupling this facility with existing programs at Crossroads and also with what the Senior Foundation is looking to do.  That’s an important factor.  We need to look at the larger picture in how the facility is utilized, if the space is just for Office for the Aging or additional programs, and neighboring facilities.

 

            Parking at the Crossroads facility was questioned.  Mr. Foels noted that their original plans wouldn’t work, as they will need about double the parking spaces on a regular basis.  They’ve changed the plans, and paving will be an IDA cost.

 

            Mr. Pullen suggested that Mr. Foels move forward to put a proposal together for a 6,000 square foot facility, and the County put together the same for the Jail site, as comparable as possible, and bring the information back to the July 9 meeting.  As far as the Belmont Betterment Association option, we’ll have to wait to see what Mr. Margeson comes back with and see how it would be laid out to accommodate our needs.

 

            Discussion was held on how a building would be placed at the Jail site, looking at the potential of adding on, entrances and new parking, and site work.  Mr. Ungermann also pointed out that we could hire a design/build team and lease the building back from them.  Mr. Carminati noted that the Jail site is a good, flat site and recommended being careful when dividing off little chunks, as it may impede future development.  Chairman Crandall noted that drawings were done during the Jail development on how the site could be parceled off.

 

            Mr. Fanton questioned some of the $120,000 costs included in the IDA proposal.  Mr. Carminati responded that they were confident these numbers are good to build a facility comparable to the existing structure.  A ten percent contingency will allow unforeseen problems to be dealt with, or it can be used for add-ons if not needed for something else.  Mr. Fanton asked if the septic system was adequate.  Mr. Carminati assumed so, as it was built for a school with larger capacities than what the senior center will require.  It still has to be tested.  Mr. Foels noted that if the County wanted some thoughts on the Jail site, the IDA would be glad to look at that also.  Mr. Carminati noted that his company has done some design/build projects, and they can work with the County on design and advise if the County’s budget for the project is adequate.  Because they work on a construction management basis, they build under different situations and have used union labor, non-union, prevailing wage, etc.; they can do what the County wants.

 

            Development of a site plan and cost estimates for the Jail site project to allow equal comparison with the IDA project will require professional assistance.  Chairman Crandall expressed concern that there were other issues not being considered and wanted to ensure proper development of the site.  This requires more than just having Mr. Margeson come back with a figure; we have to look at all figures, debt, maintenance, whether some of the work can be done in kind, etc.  Those things need to be addressed, and we need professional help.  We need a complete site plan.

 

A motion was made by Pullen, seconded by Fanton and carried to authorize County Administrator John Margeson to expend up to $5,000 for professional assistance for development of a site plan on County-owned property near the County Jail.

 

NEXT MEETING:  Wednesday, July 9 at 3:00 p.m.

 

Adjournment:  The meeting was adjourned at 5:35 p.m. following a motion made by Hall, seconded by Fanton and carried.

 

Respectfully submitted by Adele Finnemore, Journal Clerk