COMMITTEE OF THE WHOLE

JULY 28, 2008

 

** APPROVED **


Call to Order:  The meeting was called to order at 2:47 p.m. by Chairman Curtis W. Crandall.

 

Members Present: Chairman C. Crandall, G. Benson, D. Burdick, W. Dibble, D. Fanton, W. Hall, T. Hopkins, K. Kruger, M. McCormick, D. Pullen, B. Reynolds, D. Russo, R. Truax, N. Ungermann;  (Absent: T. O’Grady)

 

Guests:  LaBella Representatives M. Kukuvka and Penny Mashtare, Ciminelli Representatives,

            OCA Representative A. Isenberg

 

Court Facilities and County Office Building Presentation by LaBella Associates:

 

            Mark Kukuvka and Penny Mashtare from LaBella Associates, with assistance from representatives from their estimating team at LPCiminelli, gave a presentation on the Court Facilities Addition and Renovation and County Office Building Renovation Project (a copy of the Powerpoint presentation is attached to the original minutes).  Following selection of the Courthouse Addition option by the Court Facilities and County Space Needs Committee, LaBella’s project approach has included:

 

·         Provide pre-schematics drawings of the addition to the Courthouse

·         Provide furniture and circulation plans

·         Review and approve final pre-schematic drawings for the addition and renovation with the County and OCA

·         Meet with OCA and County department heads to establish objectives and program requirements

·         Develop pre-schematics drawings of the County Office Building showing stacking, departmental grouping, and circulation

·         Provide site plan

·         Proposed elevations

·         Cost estimate

 

            The size of the Courthouse addition has been reduced by about 6,000 square feet.  Circulation patterns have been reworked in an effort to maximize back-filling into the existing building as much as possible.  Initially a new Court entrance was to be located in back at the side of the addition, but the current plan retains the front monumental entrance of the existing Courthouse as the main entrance.  To accomplish handicapped accessibility, a ramp will be built off to the side of the main entrance.

 

            Some parking area will be lost in the back employee lot.  There will be a reduction from 141 legal spaces down to 99; a loss of 42 spaces.  This issue still needs to be resolved.  (The RFP and LaBella’s scope of work do not include off-site parking at this point.)

 

            The Department of Social Services has been reworked.  The Support Unit will be brought over to the main campus.  Records are still being maintained in the basement, but the Support building becomes available.  WIC and Cancer Services are also being brought back into the Health Department area of the main building.

 

            The “bridge” between the two existing buildings will become administrative only, with swipe-card access.  The main entry of the Courthouse will be security screening 100 percent for the entire existing Courthouse and addition.  This caused relocation of the County Treasurer’s Offices.

 


Floor Plan and Building Perspective Highlights:

 

Ground Floor, Courthouse: 

·         County Clerk records area remains

·         Probation gains some space

·         County Treasurer’s Offices relocated to front area of the addition

·         Inmate/Judge/employee shared key-code access elevator and Sheriff Sally port located in back of addition

·         Handicapped access restrooms and elevator located in core area at front of addition

·         Large “shell space” in addition remains.  (In order to maintain the monumental Courtroom and to keep Court functions together, approximately two-thirds of ground floor has been left as shell space.) 

Ground Floor, County Office Building: 

·         Health Department rearranged

·         Public Defender

·         Buildings & Grounds (part of it) in former Sally port area

·         E-911 back-up area remains

 

First Floor, Courthouse:

·         Main entry, security screening area

·         Courts

·         County Clerk’s Office stays

·         Department of Motor Vehicles back-filled into a vacated area in existing Courthouse

First Floor, County Office Building:

·         Department of Social Services has been reworked and is expanding to two floors

 

Second Floor, Courthouse:

·         Courts and hearing rooms, retained monumental Courtroom

·         Judges’ chambers reworked a little

·         Handicapped access restrooms located in core area

·         Some additional shell space for future expansion (roofed in, but not finished off)

Second Floor, County Office Building:

·         Department of Social Services expanded into one-half of the floor

·         Department of Public Works has been given more space (the department remains in the main building to save money, rather than moving them off-site)

·         Information Technology relocated to get the equipment out of the basement

 

Third Floor, County Office Building (former Jail):

·         Moved some of the offices currently on the second floor up to the third floor: Legislative Chambers/Grand Jury, Clerk of the Board’s Office, County Administrator, Human Resources, District Attorney, County Attorney

 

Building Perspectives:

·         Front entrance showing the handicapped ramp

·         Addition showing the Judges’ entry which ties into the appearance of the main entrance and the Sally port

 

Cost Estimates for Courthouse and County Office Building:

 

            LaBella put together very comprehensive data on their pre-schematic design including a demolition plan, narratives, IT system, structural system, analysis of existing building, etc., which gave their estimating team at Ciminelli a lot of information to work with to compile their cost estimates.  The estimate has been broken down by project components; the square footage and cost estimate for each component are indicated below:

 

            Courthouse Renovation:                       9,600 sf                     $  1,852,000

            Courthouse Addition:                          42,000 sf                       11,935,000

            County Office Building Renovation:    33,000 sf                         4,897,000

                        Total Project:                           84,600 sf                     $18,684,000

 

            Costs are inclusive project costs (including contingencies, construction manager fees, bonding costs, etc.) and are adjusted for inflation according to the assumption that construction will begin Fall 2009, construction mid-point Summer 2010.  (For comparison purposes, the September 2007 proposal included a total project square footage of 97,700 at a cost estimate of $22,678,000; current estimates have been reduced by nearly $4 million.)

 

Discussion (Responses by LaBella’s Mark Kukuvka are italicized):

 

            Mr. Reynolds questioned if the estimates include equipment and furniture.  (Kukuvka:  The plan includes trying to salvage as much as possible to save costs.)

 

            Mr. Ungermann asked what square footage in the addition is for Court use.  (Kukuvka:  Court functions are assigned to nearly all of the first and second floors, and not much of the ground floor, or approximately two-thirds of the addition.)  Mr. Ungermann noted that there are a lot of excluded costs, such as high-density storage, fixtures, and equipment.  (Kukuvka:  LaBella worked with the County and OCA to be sure all reasonable items are included in the bonding, minus salvaged equipment and furniture.  Although excluded in earlier iterations, high-density storage is now included.  The full report will be left with County Administrator John Margeson.)

 

            Mr. Truax questioned the plans for the addition ground floor shell space, and wondered if it wouldn’t be better to eliminate a floor.  (Kukuvka:  The goal was to keep the existing Courtroom, and to keep Court functions contiguous on the same floors between the existing building and the addition.)  Mr. Truax suggested using the shell space for the offices slated to be moved to the former jail floor, saving those renovation costs.  (Kukuvka:  Practicality, accessibility, and adjacencies were considered in the placement of offices, and there were not a lot of options for what could be put in the former jail space.)  Mr. Truax noted that we’re paying a lot to build the addition, but we’re leaving a lot of space vacant.  It could be used for maintenance and storage.  (Kukuvka:  The shell space provides the County with space for future expansion as cheaply as possible.) 

 

            Mr. Pullen referred to conversations held with other counties that have gone through this process and already have encountered problems with storage space deficiencies and lack of space to address changes in Court structure, i.e. additional courts.  Our County was encouraged to allow for flexibility.  It may be cheaper to not include the shell space, but it will never be cheaper to build than it is now.  This plan offers the longest term approach with the shortest term effect for taxpayers.

 

            Mr. Reynolds commented that the former jail space has to be utilized.  Mr. Truax asked if it could be used for storage.  (Kukuvka:  That space works for offices, but the floor loading rating is not adequate for high-density storage.)

 

            Mr. Ungermann asked if the estimates include a new roof over the entire former jail.  (Kukuvka:  No, only the recreation yard which will be built in.)  Mr. Ungermann asked whether Information Technology work is included in the estimate.  (Kukuvka:  Wiring and conduit is provided for, but the rest would be done by Information Technology.  A lot of the detailed listing includes assumptions, and it’s uncertain how much equipment will be salvaged.  Also not included in the estimates is off-campus parking.)

 

            Mr. Ungermann questioned the estimate for renovations per square foot.  (Kukuvka:  That would be a difficult number to pin down due to the nature of the project.  Some areas will only require “scrape and paint,” some need wholesale major renovation, as is the case with the former jail floor.  It’s a blend of so many levels of renovation.  The per square foot estimate for some areas will be close to $300, and for some areas it will be as low as $10-15.)

 

            Chairman Crandall referred to discussion at the last Court Facilities Committee meeting about escalating building material and construction costs.  He was left with the feeling that there was ample coverage for projected escalations.  Chairman Crandall had questioned the percentages for contingencies and soft costs, amounting to several million dollars to cover the unknowns.  Even though the project has gone through extensive analysis, that’s what these contingencies are for.  We won’t know if this estimate is a comfortable number until we go out to bid and get some specific dollar amounts, but there are no hidden numbers.  (Kukuvka:  That is correct.  The amount included for contingencies is reasonable for this phase of the project.)

 

            Mr. Reynolds asked about LaBella’s past experience on how the contingencies have run.  (Kukuvka:  He doesn’t like to tamper with contingencies this early in the process.  LaBella has a good record for building at less than what they allow for contingencies, but it’s too early to say that.  It’s different with every project.  Renovations cause the biggest unknowns.)

 

            Mr. McCormick questioned if enough public space is included in the addition plans.  Mr. Pullen noted that it’s difficult to see on the floor plans, but there is a seating area for 20 people at the end of the corridor.  We don’t presently have that.  There are also attorney/client areas, seating in various Court Clerk areas, numerous areas to conference and wait, and a children’s area (as required by OCA).

 

            Mr. Ungermann commented that the open shell space on the second floor of the addition covers the windows over the existing Court staircase.  (Kukuvka:  The plan is to put some back-lights in so the stained glass will be lighted from behind, or possibly a small sky light.)

 

            Andrew Isenberg, OCA, advised the Legislature that the Courts have worked collaboratively with the Court Facilities Committee, and he feels that they have worked tirelessly to make certain that the scale and scope of the plan is adequate to accommodate the Courts.  The project has been scaled back as much as possible.  Mr. Isenberg expressed his appreciation for all their efforts.

 

            Mr. Pullen recommended that if there are any questions, legislators should contact him or Mr. Margeson prior to the next Court Facilities meeting on August 6.  The committee will try to find the answers and implement suggestions to refine the plan for the best possible outcome.  The Court Facilities Capital Plan will come before the full Board for approval within the next few weeks.

 

            Mr. Kruger asked when the unresolved problems, such as off-site parking, will be addressed, and if those costs would be included in the bond.  Chairman Crandall responded that some conversation has taken place, and the bond will cover whatever needs to be included, unless there are other options.  Mr. Ungermann questioned if energy costs have been put together.  Mr. Kukuvka noted that they have not.  Mr. Pullen noted that it is a possibility to work with and receive guidance from NYSERDA, and there are programs available.  Participation will increase short-term costs, but there is a long-term pay back.  LaBella is working on it.  Chairman Crandall noted that lighting, heating, etc. are included with any construction project, and some projection is necessary.

 

Attorney/Client Session:  A motion was made by Legislator McCormick, seconded by Legislator Fanton and carried to enter into an Attorney/Client Session.  Following discussion, a motion was made by Legislator Reynolds, seconded by Legislator Hall and carried to end the Attorney/Client Session.

 

Adjournment:  The meeting was adjourned following a motion made by Legislator Reynolds, seconded by Legislator Hall and carried.

 

Respectfully submitted,

Adele Finnemore, Journal Clerk